Europe can announce a factory, support a data centre and finance new electricity generation. Yet none of these commitments guarantees that electricity will reach the right place at the right time.

Between an economic ambition and its delivery stand cables, transformers, conversion equipment, permits and teams capable of installing them. This work attracts less attention than an inauguration. It can nevertheless determine its date.

The report published by ENTSO-E on 3 November 2026 provides a useful starting point for understanding this constraint. Our investor question follows: which companies can deliver this infrastructure while earning an adequate return on the capital they must commit?

What the figures say — and their limits

Reported data — ENTSO-E. The survey covers 27 transmission system operators in 24 countries. Planned additions for 2026–2035 include approximately 34,000 conductor-kilometres of HVDC cables, 2,820 power transformers and 119 bipolar converter stations. Installations are expected to peak between 2028 and 2032. [1][2]

Specifically, operators plan 22,303 conductor-kilometres of underground direct-current cables and 11,687 conductor-kilometres of submarine direct-current cables, alongside the 2,820 power transformers and 119 bipolar HVDC converter stations by 2035.

Source: ENTSO-E, Table 1, page 8. Conductor-kilometres are not route-kilometres.

These volumes include replacement and expansion; asset retirements are not recorded. Coverage is incomplete and longer-term intentions remain subject to revision. The figures therefore measure neither net grid expansion, nor firm orders, nor suppliers’ future revenue. [2]

Timing becomes an economic variable

In 2025, the IEA documented procurement lead times of two to three years for cables and up to four years for large transformers. Some direct-current cables required more than five years. It also identified permitting as the leading cause of transmission project delays, particularly in advanced economies. [3]

MITUXA View. The implications extend beyond electricity. For a manufacturer, an uncertain connection date can make a location less attractive even if it is competitive on wages, taxes or the theoretical price of energy.

Equipment purchased too early ties up funds. Equipment delivered too late delays operations. Companies must coordinate commitments that do not all follow the same timetable.

The ability to meet a date thus becomes part of competitiveness. A region offering a credible grid connection can provide economic value that conventional cost comparisons do not fully capture.

Industrial scarcity does not guarantee profitability

The quickest stock-market argument links greater needs to greater profits. Several steps are missing.

A cable factory must be financed, built, qualified and then used. Contracts must adequately protect suppliers against rising costs. Execution must avoid penalties. Customers must pay on a schedule compatible with the expenditure incurred.

Two companies exposed to the same cycle can therefore deliver very different outcomes. One may have qualified capacity, well-structured contracts and strong cash conversion. Another may accumulate low-return orders and consume cash fulfilling them.

The MITUXA test: once capacity has ramped up, will the additional operating profit generate a return on the additional capital above its cost?

A backlog offers information about future activity. On its own, it does not answer that question.

Prysmian and NKT: two concrete research cases

On 2 February 2026, National Grid announced a £2 billion cable contract awarded to Prysmian for Eastern Green Link 4. The 2 GW HVDC connection is intended to link Scotland and England. The announced timetable targets operation in 2033, with construction expected to start in 2029, subject to consent. [4]

This illustrates the distance between a commercial announcement and an operational asset. Our interpretation: analysing the supplier requires understanding advance payments, manufacturing and installation expenditure, contractual protections and the allocation of delay risks. A contract’s headline value is not its value to shareholders.

At its investor day on 29 September 2026, NKT presented the execution of its €2 billion investment programme as a central priority. Management now expects the Karlskrona expansion to begin commercial operations in the second quarter of 2027. This is a management forecast, not capacity already available. [5]

Our interpretation: the next important evidence will be industrial. Meeting the timetable, the quality of initial production and equipment utilisation will matter as much as backlog growth.

Prysmian and NKT are research examples here. This article makes no valuation judgement or buy call on either company.

Who bears the cost of time?

The cost of capital matters before a grid carries its first kilowatt-hour.

Consider a purely hypothetical illustration: an average financing balance of €500 million facing an additional percentage point of interest implies €5 million in extra annual financing costs. The actual effect depends on debt terms, hedging, maturities and the disbursement schedule. This calculation describes none of the projects cited here.

For a regulated operator, the question is which investments are recognised, when, and at what allowed return. For a manufacturer, it includes working-capital financing and the returns from new factories. For consumers, it appears through tariffs and service quality.

It would therefore be premature to promise an immediate reduction in electricity bills simply because more grids are built. Better infrastructure can reduce constraints and improve system utilisation. Its financing can simultaneously increase certain tariff components. The net outcome must be demonstrated market by market.

Europe’s response must be industrial and financial

MITUXA View. Credible policy should balance visibility with discipline.

Visibility allows suppliers to prepare capacity. Discipline prevents every announced project from becoming an irreversible expense before its need, financing and permits are sufficiently established.

Competition must also be preserved. Early reservations can secure manufacturing slots; they can also increase financial commitments or concentrate dependence on a supplier. Procurement quality cannot be measured by the initial price alone.

A meaningful comparison incorporates lifetime costs, reliability, delivery times, maintenance options and contractual terms. The cheapest supplier on paper does not necessarily minimise total cost. The most expensive does not automatically deserve an unverified quality premium.

What we will monitor

First: are projects becoming executable? We will track permits, financing and actual construction starts. Repeated postponements or cancellations would weaken demand visibility.

Second: is industrial capacity arriving on time? Qualification and commissioning will be decisive. Delays, manufacturing defects or cost overruns could prevent suppliers from converting orders into earnings.

Third: is growth turning into cash? We will examine cash flow after capital expenditure, accounting for customer advances and working capital. Rising profits alongside persistently weak cash generation would be a warning.

Fourth: is capital creating value? After ramp-up, new capacity must earn an adequate return on the capital committed. Strong activity would not compensate for inadequate investment returns.

Fifth: is the share price reasonable? Valuations should be tested against normalised margins and utilisation rates. A price requiring years of perfect execution would leave little room for disappointment.

The favourable scenario combines executable projects, capacity delivered on time and contractual discipline. The adverse scenario can take two forms: delayed investments leaving factories underutilised, or simultaneous capacity expansion eventually compressing margins. Strong structural demand eliminates neither risk.

MITUXA’s conviction concerns the grid’s economic importance. Equity selection remains conditional on execution, cash flow and the price paid.

Europe becomes more competitive if infrastructure arrives on time and at a sustainable cost. Shareholders benefit only if the selected company captures some of that value without committing too much capital — and if success was not already fully reflected in its share price.

Sources and scope

Analysis prepared on 11 November 2026; English edition published on 12 November 2026. Institutional figures are published data or projections; future industrial dates are issuer forecasts. Interpretations and monitoring criteria are MITUXA’s. This article does not construct consensus forecasts, company valuations or expected equity returns.

  1. ENTSO-E — announcement, 3 November 2026.
  2. ENTSO-E — Transmission Grid Investment and Supply Chain Assessment Report 2026, particularly pages 7–8, 11 and 33. Figures cover transmission within the respondents’ scope, not all European transmission and distribution.
  3. IEA — Building the Future Transmission Grid, executive summary, 2025. Lead times are those documented in that study, not an updated November 2026 measurement.
  4. National Grid — Eastern Green Link 4 cable contract with Prysmian, 2 February 2026.
  5. NKT — Investor Day, 29 September 2026.

Independent research for information and educational purposes only. This is not personalised financial advice or a recommendation to buy or sell.

MITUXA — Beyond the Obvious. Follow our company and economic research: subscribe to MITUXA. Contact: questions@mituxa.com.